The Mutiara Line: where the build stands

The Mutiara Line was 8.99% complete as at June 2026, according to the Transport Ministry, with operations targeted for December 2031. In August its RM3.028 billion systems contract — trains, signalling, track, power and fare collection — was awarded to the MRCB–Theta Edge joint venture. The planned Permatang Damar Laut station (S02) is 4.6 km from Southbay, as published by the developer.

8.99%Transport

Where the build stands

In a written reply reported by The Star on 24 June 2026, the Transport Ministry put the 29.67 km line at 8.99% complete, with operations targeted for December 2031. Most of the build is still ahead.

The Silicon Island–Komtar section shows what progress looks like on the ground. FMT, carrying a Bernama report on 6 August 2026, said 93% of its land was available, work had started on 14 of the 19 sections along it, 45 pile caps and 32 pier columns had been built, and soil investigation had begun for the depot on Silicon Island.

The contracts

The RM3.028 billion system turnkey contract is one package for everything that makes the line run: trains, signalling, track, power and fare collection. Malay Mail and FMT reported on 6 August 2026 that it had gone to the MRCB–Theta Edge joint venture.

The Komtar–Penang Sentral section is at an earlier stage. The Edge reported the same day that its contract award is targeted for November 2026.

Sources

  1. The Star, 24 June 2026 — Transport Ministry written reply: the 29.67 km line 8.99% complete as at June 2026; operations targeted for December 2031
  2. Malay Mail, 6 August 2026 — the RM3.028 billion system turnkey contract (trains, signalling, track, power, fare collection) awarded to the MRCB–Theta Edge joint venture
  3. FMT, 6 August 2026 — the systems contract award; and, from Bernama, progress on the Silicon Island–Komtar section: 93% of land available, work on 14 of 19 sections, 45 pile caps and 32 pier columns built, depot soil investigation begun on Silicon Island
  4. The Edge, 6 August 2026 — Komtar–Penang Sentral contract award targeted for November 2026
  5. The developer's nearby-amenities sheet, 2026 — Permatang Damar Laut station (S02) 4.6 km from Southbay
  6. The developer's M Amaya FAQ — expected completion, 2030

Published 6 August 2026

Speak to Kevin

Talk it through with Kevin.

Ask how it bears on M Amaya — the layout, the timing and the numbers.

Kevin Lee

Kevin Lee · REN 14973 · FLP Realty Sdn Bhd · E(1) 1718

Kevin replies personally. Your details are never sold — the privacy notice says what he receives and why. Privacy notice

Ask KevinWhatsApp · English, 中文, BM